This thread will house the planning minutes.
Sprint 103
12-Aug-2021
New Sprint 103 query: Sprint 103 - Pulp
New Agile board: https://pup.plan.io/agile/board?query_id=151
Stats on how we did in previous sprint Sprint 102 Query
New - 36
Assigned - 11
Post - 11
Modified - 18
Closed - CURRENTRELEASE - 7
Closed - WORKSFORME -
Closed - NOTABUG - 1
Closed - DUPLICATE -
Closed - WONTFIX - 2
Closed - COMPLETE - 1
Action Items:
- [x] Create new sprint value here: https://pulp.plan.io/custom_fields/39/edit
- [x] rchan: post minutes (and pulp-dev?)
- [x] Rchan update agile board for sprint & Move new, assigned, post issues to new sprint
- [x] Rchan: Publish Sprint Plans - Pulp
Stakeholder Delivery Dates:
- Satellite 6.10 BZs priority in this sprint
- New Beta BZ freeze list
- Post-beta, opens back up for fixes
-
Katello: Keeping short term deadlines and started discussing
- 4.2 branching ~August 2021
- Alternate Content Sources
- 4.3 Branching ~Nov 2021
- 4.2 branching ~August 2021
- Ansible
- AH 4.4.0 release (November)
- AH performance and scale testing ( ansible and container plugins)
Dates & Content:
https://pulp.plan.io/projects/pulp/wiki/Sprint_Plans
Sprint candidates:
https://pulp.plan.io/issues?query_id=26
Items put on hold:
-
Planning for logging changes (ggainey, bmbouter)(core)
-
Making pulp logging more configurable · Discussion #20 · pulp/community · GitHub
-
Release automation - bindings docs (dkliban) (CI/CD)
-
Github Issue migration (david/dkliban) (CI/CD)
-
RTD x docs.pulpproject.org (mcorr)
26-Aug-2021
New Sprint 104 query: Sprint 104 - Pulp
New Agile board: https://pup.plan.io/agile/board?query_id=151
Stats on how we did in previous sprint Sprint 103 Query
New - 35
Assigned - 12
Post - 7
Modified - 7
Closed - CURRENTRELEASE - 21
Closed - WORKSFORME -
Closed - NOTABUG -
Closed - DUPLICATE -
Closed - WONTFIX -
Closed - COMPLETE -
Action Items:
- [x] Create new sprint value here: https://pulp.plan.io/custom_fields/39/edit
- [x] rchan: post minutes on discourse
- [x] Rchan update agile board for sprint & Move new, assigned, post issues to new sprint
- [x] Rchan: Publish Sprint Plans - Pulp
Action Items from last Sprint Planning
- Update 3 month planning current quarter line item status
Stakeholder Delivery Dates:
- Satellite 6.9 and 6.10 BZs priority in this sprint
- Migration fixes for 6.9
- Post-beta, opens back up for fixes
-
Katello: Keeping short term deadlines and started discussing
- 4.2 branching ~August 2021
- Alternate Content Sources
- 4.3 Branching ~Nov 2021
- 4.2 branching ~August 2021
- Ansible
- AH 4.4.0 release (November)
- AH performance and scale testing (ansible and container plugins)
- DRF token support will be moving out (will get confirmation)
- Will discuss synclist release plan w/Hub
Dates & Content:
https://pulp.plan.io/projects/pulp/wiki/Sprint_Plans
Sprint candidates:
https://pulp.plan.io/issues?query_id=26
Items put on hold:
- Planning for logging changes (ggainey, bmbouter)(core)
- Release automation - bindings docs (dkliban) (CI/CD)
- Github Issue migration (david/dkliban) (CI/CD)
- RTD x docs.pulpproject.org (mcorr)
- Plugin removal (ttereshc)
- Static enable/disable for commands for Katello (mdellweg) (CLI)
- blog post RE ostree for fedoramagazine (dkliban, mcorr)
Sprint 105
9-Sept-2021
New Sprint 105 query: Sprint 105 - Pulp
New Agile board: https://pup.plan.io/agile/board?query_id=151
Stats on how we did in previous sprint Sprint 104 Query
New - 39
Assigned - 11
Post - 12
Modified - 14
Closed - CURRENTRELEASE - 6
Closed - WORKSFORME - 1
Closed - NOTABUG - 1
Closed - DUPLICATE -
Closed - WONTFIX -
Closed - COMPLETE -
Action Items:
-
[x] Create new sprint value here: https://pulp.plan.io/custom_fields/39/edit
-
[x] rchan: post minutes on discourse
-
[x] Rchan update agile board for sprint & Move new, assigned, post issues to new sprint
-
[x] Rchan: Publish Sprint Plans - Pulp
Action Items from last Sprint Planning
- Update 3 month planning current quarter line item status
- Rchan will ask follow up on priority of drf token work. on hold until then.
Stakeholder Delivery Dates:
-
Satellite 6.9 and 6.10 BZs priority in this sprint
- Migration fixes for 6.9
- 6.10 GA blockers, BZ freeze Sep 29
- Satellite deadlines for both 6.9 and 6.10 are currently around end of September
-
Katello: Keeping short term deadlines and started discussing
- 4.2 branching ~August 2021
- Alternate Content Sources
- 4.3 Branching ~Nov 2021
- 4.2 branching ~August 2021
-
Ansible
- AH 4.4.0 release (November)
- AH performance and scale testing (ansible and container plugins)
- DRF token support will be moving out (will get confirmation)
- Will discuss synclist release plan w/Hub
Dates & Content:
https://pulp.plan.io/projects/pulp/wiki/Sprint_Plans
Sprint candidates:
https://pulp.plan.io/issues?query_id=26
Items put on hold:
-
Planning for logging changes (ggainey, bmbouter)(core)
-
Release automation - bindings docs (dkliban) (CI/CD)
-
Github Issue migration (david/dkliban) (CI/CD)
-
Plugin removal (ttereshc)
-
Static enable/disable for commands for Katello (mdellweg) (CLI)
-
blog post RE ostree for fedoramagazine (dkliban, mcorr)
-
drf token auth (including determining if still needed)
-
Support signed repo metadata PR fixes (when they arrive) → Q2
Sprint 106
23-Sept-2021
New Sprint 106 query: Sprint 106 - Pulp
New Agile board: https://pup.plan.io/agile/board?query_id=151
Stats on how we did in previous sprint Sprint 105 Query
New - 38
Assigned - 14
Post - 10
Modified - 29
Closed - CURRENTRELEASE - 7
Closed - WORKSFORME -
Closed - NOTABUG -
Closed - DUPLICATE - 2
Closed - WONTFIX - 1
Closed - COMPLETE -
Action Items:
-
[] rchan: post minutes on discourse
-
[x] Rchan update agile board for sprint & Move new, assigned, post issues to new sprint
-
[x] Rchan: Publish Sprint Plans - Pulp
Action Items from last Sprint Planning
- Rchan will ask follow up on priority of drf token work. on hold until then.
- Confirmed!
Stakeholder Delivery Dates:
-
Satellite BZs priority in this sprint
- Migration fixes for 6.9
- Satellite deadlines for currently around end of September
-
Katello: Keeping short term deadlines and started discussing
- 4.2 branching ~August 2021
- 4.3 Branching ~Nov 2021
- Alternate Content Sources
-
Ansible
- AH 4.4.0 release (November)
- AH performance and scale testing (ansible and container plugins)
- Will discuss synclist release plan w/Hub
- Content signing planning for collections and containers
Dates & Content:
https://pulp.plan.io/projects/pulp/wiki/Sprint_Plans
Sprint candidates:
Sprint 107
7-Oct-2021
New Sprint 106 query: Sprint 107 - Pulp
New Agile board: https://pup.plan.io/agile/board?query_id=151
Stats on how we did in previous sprint Sprint 106 Query
New - 36
Assigned - 11
Post - 12
Modified - 14
Closed - CURRENTRELEASE - 22
Closed - WORKSFORME -
Closed - NOTABUG - 1
Closed - DUPLICATE -
Closed - WONTFIX -
Closed - COMPLETE - 1
Action Items:
-
[x] rchan: post minutes on discourse
-
[x] Rchan update agile board for sprint & Move new, assigned, post issues to new sprint
-
[x] Rchan: Publish Sprint Plans - Pulp
-
[x] Create new sprint value here: https://pulp.plan.io/custom_fields/39/edit
Action Items from last Sprint Planning
- none
Stakeholder Delivery Dates:
-
Satellite 6.9 and 6.10 BZs priority in this sprint
- Migration fixes for 6.9.z
- 6.10 GA blockers
-
Katello: Keeping short term deadlines and started discussing
- 4.2 branching ~August 2021
- 4.3 Branching ~Nov 2021
- Alternate Content Sources
-
Ansible
- AH 4.4.0 release (November)
- AH performance and scale testing (ansible and container plugins)
- Will discuss synclist release plan w/Hub
- Content signing planning for collections and containers
Dates & Content:
https://pulp.plan.io/projects/pulp/wiki/Sprint_Plans
Sprint candidates:
21-Oct-2021
New Sprint 108 query: Sprint 108 - Pulp
New Agile board: https://pup.plan.io/agile/board?query_id=151
Stats on how we did in previous sprint Sprint 107 Query
New - 37
Assigned - 9
Post - 14
Modified - 10
Closed - CURRENTRELEASE - 5
Closed - WORKSFORME -
Closed - NOTABUG -
Closed - DUPLICATE -
Closed - WONTFIX -
Closed - COMPLETE - 2
Action Items:
- [x] rchan: post minutes on discourse
- [x] Rchan update agile board for sprint & Move new, assigned, post issues to new sprint
- [x] Rchan: Publish Sprint Plans - Pulp
- [x Create new sprint value here: https://pulp.plan.io/custom_fields/39/edit
- [x] Update 3 month planning current quarter line item status
Action Items from last Sprint Planning
- none
Stakeholder Delivery Dates:
-
Satellite 6.9 and 6.10 BZs priority in this sprint
- Migration fixes for 6.9.z
- 6.10 GA blockers
-
Katello: Keeping short term deadlines and started discussing
- 4.2 branching ~August 2021
- 4.3 Branching 5-Nov 2021
- Alternate Content Sources
- OSTree integration
-
Ansible
- AH 4.4.0 release
- AH performance and scale testing (ansible and container plugins)
- Will discuss synclist release plan w/Hub
- Content signing planning for collections and containers
Dates & Content:
https://pulp.plan.io/projects/pulp/wiki/Sprint_Plans
Sprint 109
4-Nov-2021
Note that PulpCon will be happening during this Sprint and impact staffing for development.
New Sprint 109 query: Sprint 109 - Pulp
New Agile board: https://pup.plan.io/agile/board?query_id=151
Installer Issues: https://github.com/pulp/pulp_installer/issues
Stats on how we did in previous sprint Sprint 108 Query
New - 29
Assigned - 16
Post - 22
Modified - 4
Closed - CURRENTRELEASE - 3
Closed - WORKSFORME -
Closed - NOTABUG -
Closed - DUPLICATE - 1
Closed - WONTFIX -
Closed - COMPLETE -
Action Items:
-
[x] rchan: post minutes on discourse
-
[x] Rchan update agile board for sprint & Move new, assigned, post issues to new sprint
-
[x] Rchan: Publish Sprint Plans - Pulp
-
[x] Create new sprint value here: https://pulp.plan.io/custom_fields/39/edit
Action Items from last Sprint Planning
- none
Stakeholder Delivery Dates:
-
Satellite 6.9 and 6.10 BZs priority in this sprint
- Migration fixes for 6.9.z
- 6.10 blockers
-
Katello: Keeping short term deadlines and started discussing
- 4.3 Branching 5-Nov 2021
- OSTree integration
- 4.3 Branching 5-Nov 2021
-
Ansible
- AH 4.4.0 release
- AH performance and scale testing (ansible and container plugins)
- Will discuss synclist release plan w/Hub
- Content signing planning for collections and containers
Dates & Content:
https://pulp.plan.io/projects/pulp/wiki/Sprint_Plans
Items put on hold:
-
Release automation - bindings docs (dkliban) (CI/CD)
-
blog post RE ostree for fedoramagazine (dkliban, mcorr)
-
Backporting automation proposal
-
Implement Pulp 101 feedback from everyone (Community)
-
Write up how to integrate Jenkins with your Pulp instance
Sprint 110
18-Nov-2021
New Sprint 110 query: Sprint 110 - Pulp
New Agile board: https://pup.plan.io/agile/board?query_id=151
Installer Issues: https://github.com/pulp/pulp_installer/issues
Stats on how we did in previous sprint Sprint 109 Query
New - 27
Assigned - 14
Post - 22
Modified - 4
Closed - CURRENTRELEASE - 2
Closed - WORKSFORME -
Closed - NOTABUG -
Closed - DUPLICATE -
Closed - WONTFIX - 1
Closed - COMPLETE -
Action Items:
-
[x] rchan: post minutes on discourse
-
[x] Rchan update agile board for sprint & Move new, assigned, post issues to new sprint
-
[x] Rchan: Publish Sprint Plans - Pulp
-
[x] Create new sprint value here: https://pulp.plan.io/custom_fields/39/edit
-
[x] Update 3 month planning current quarter line item status
Action Items from last Sprint Planning
- none
Stakeholder Delivery Dates:
-
Satellite 6.9 and 6.10 BZs priority in this sprint
- Migration fixes for 6.9.z
- 6.10 customer reports
-
Katello: Keeping short term deadlines and started discussing
-
Ansible
- AH 4.4.0 release
- AH performance and scale testing (ansible and container plugins)
- Content signing for collections and containers (February)
- upcoming GA date for AAP on Azure
- Work supporting galaxy.ansible.com replacement (no specific dates)
Dates & Content:
https://pulp.plan.io/projects/pulp/wiki/Sprint_Plans
Items put on hold:
-
Release automation - bindings docs (dkliban) (CI/CD)
-
Backporting automation proposal
-
CLI - pulp_rpm content commands (advisory, modulemd, etc)
Sprint 111
2-Dec-2021
New Sprint 110 query: Sprint 111 - Pulp
New Agile board: https://pup.plan.io/agile/board?query_id=151
Installer Issues: https://github.com/pulp/pulp_installer/issues
Stats on how we did in previous sprint Sprint 110 Query
New - 25
Assigned - 16
Post - 10
Modified - 7
Closed - CURRENTRELEASE - 10
Closed - WORKSFORME -
Closed - NOTABUG -
Closed - DUPLICATE -
Closed - WONTFIX -
Closed - COMPLETE - 1
Action Items:
-
[x] rchan: post minutes on discourse
-
[x] Rchan update agile board for sprint & Move new, assigned, post issues to new sprint
-
[x] Rchan: Publish Sprint Plans - Pulp
-
[x] Create new sprint value here: https://pulp.plan.io/custom_fields/39/edit
-
[x] Update 3 month planning current quarter line item status
Action Items from last Sprint Planning
- none
Stakeholder Delivery Dates:
-
Satellite 6.9 and 6.10 BZs priority in this sprint
- Migration fixes for 6.9.z
- 6.10 customer reports
-
Katello: Keeping short term deadlines and started discussing
-
Ansible
- AH performance and scale testing (ansible and container plugins)
- Content signing for collections and containers (February)
- Work supporting galaxy.ansible.com replacement (no specific dates)
Non-redmine/github issues impacting capacity:
- Hiring + end of year PTO
Dates & Content:
https://pulp.plan.io/projects/pulp/wiki/Sprint_Plans
Items put on hold:
-
Release automation - bindings docs (dkliban) (CI/CD)
-
Backporting automation proposal
-
CLI - pulp_rpm content commands (advisory, modulemd, etc)
Sprint 112
6-Jan-2022
New Sprint 112 query: Sprint 112 - Pulp
New Agile board: https://pup.plan.io/agile/board?query_id=151
Installer Issues: https://github.com/pulp/pulp_installer/issues
Stats on how we did in previous sprint Sprint 111 Query
- We are half-moved to github issues so this query is only pulpcore
- How are we going to get this info from github?!?
New - 11
Assigned - 8
Post - 6
Modified - 7
Closed - CURRENTRELEASE - 16
Closed - WORKSFORME -
Closed - NOTABUG - 2
Closed - DUPLICATE - 27
Closed - WONTFIX - 1
Closed - COMPLETE -
Action Items:
-
[x] rchan: post minutes on discourse
-
[x] Rchan update agile board for sprint & Move new, assigned, post issues to new sprint
-
[x] Rchan: Publish Sprint Plans - Pulp
-
[x] Create new sprint value here: https://pulp.plan.io/custom_fields/39/edit
-
[] Update 3 month planning current quarter line item status
-
[] ggainey: Investigate github-issue options for running this mtg
Action Items from last Sprint Planning
- none
Stakeholder Delivery Dates:
-
Satellite 6.9 and 6.10 BZs priority in this sprint
- Migration fixes for 6.9.z
- 6.10 customer reports
-
Katello: Keeping short term deadlines and started discussing
-
Ansible
- Content signing for collections and containers (February)
- Work supporting galaxy.ansible.com replacement (no specific dates)
Dates & Content:
https://pulp.plan.io/projects/pulp/wiki/Sprint_Plans
Items put on hold:
-
Release automation - bindings docs (dkliban) (CI/CD)
-
CLI - pulp_rpm content commands (advisory, modulemd, etc)